The company’s “foot is on the accelerator” to close data center deals as it works to restart Three Mile Island Unit 1 by 2027 ...
Amazon’s (NASDAQ:AMZN) plan to build a data center powered by a Pennsylvania nuclear power plant has not changed, even as the ...
Nuclear plant owner Talen Energy Corp. says an initial 300 MW of data center development can proceed despite feds' rejection of grid link agreement to its Susquehanna facility in Pennsylvania's ...
The commission agreed with opponents of the proposal, citing concerns about grid reliability and cost fairness.
Importantly, the existing ISA allows for 300 megawatts of co-located load at Susquehanna, and development of the first phases of the Amazon Web Services (“AWS”) data center campus can proceed using ...
Talen Energy (TLN) released the following statement in response to Friday’s Federal Energy Regulatory Commission, the ...
By denying Talen’s revised agreement, FERC is emphasizing that it would “continue to prioritize grid reliability and ...
Nuclear stocks are trading lower across the board on Monday after regulators rejected Talen Energy Corp's (NASDAQ:TLN) plans ...